Our Registered Office changed to 13B, Bidhan Sarani, 4th Floor, Kolkata - 700 006

Past Projects

Sl No. Description of Work Purchaser Section / Group TKM / No. of TSS
20
Design,Supply,Erection,Testing and Commissioning of 25 KV A.C.Single Phase,50 HZ,Traction Overhead Equipments,Switching Stations Booster Transformer Stations including foundations,structures and all ancillary equipments for Shakoorbasti(Excl)-Rohtak (incl) section of Delhi Division of Northern Railway under RE Project,Ambla.Total RKMs-60/TKMs-145
Chief Electrical Engineer Central Organisation for Railway Electrification Allahabad.
Northern Railway
179.823 TKM
21
Design,Supply,Erection,Testing & Commissioning of 25 KV OHE work of 4th line between Asoati and palwal including both the yards.
Chief Electrical Engineer/CON, Northern Railway.
Northern Railway
30 TKM
22
Provision of New 132 KV/25 KV Single Transformer Traction Sub-Station behind Bidhannagar Road/ SSP Near Chitpur Terminal Station in Sealdah Division of Eastern Railway.
Additional Divisional Manager Eastern Railway, Sealdah.
Eastern Railway
1 nos TSS work
23
Design,Supply,Erection, Testing & Commissioning of 25 KV OHE for the work of Provision of 66/25 KV traction Sub Station at Parwanoo and 25 KV feeder line/SSP.
Chief Electrical Engineer/Const,Northern Railway, New Delhi.
Northern Railway
TSS
24
25KV, 50 Hz, Single Phase AC, OHE & TSS Works in Singapur Road (Excl) – Damanjodi (Incl) Section, Gr 181 of Waltair Division of East Coast Railway under RE Project Bhubaneswar, Total 152 RKM/179 TKMs.
Chief Electrical Engineer/CON, Eastern Railway, Fairly Place, Kolkata.
Eastern Railway
TSS
25
Supply of OHE mast, Contact Wire, OHE Equipment & All Accessories necessary for 25 KV AC Traction Overhead Equipment System and Electrical Equipment for balance doubling work and All Accessories necessary for Construction of 25 KV Switching Station Post(SSP) at DZK station in connection with Doubling work between BYSA & DZK.
Haldia Energy Limited
Haldia Energy Limited
1.3 TKM
26
Design, Drawing, Supply, Erection, Testing & Commissioning of 25 KV a.c Single Phase Overhead Equipment, LT supply transformer & switching station at Khanyan & Bainchi in connection with construction 3rd line between Talandu(ExcL) and Bainchi(IncL) (Excluding removal of infringements required for opening of Engineering Siding from Talandu to Bainchi) in Howrah Division of Eastern Railway.
Chief Electrical Engineer/CON, Fairly Place, Kolkata.
Eastern Railway
27 TKM
27
Design, Drawings, Supply, Erection, Testing & Commissioning of Electrification of Track Hooper Line, Engine Escape Line within Plant Area of Kolaghat Thermal Power Station of WBPDCL,WB.
Group General Manager Rites Ltd, Kolkata.
WBPDCL,RITES LTD.
9.5
28
Design, Drawing, Supply, Erection, Testing & Commissioning of 25 KV a.c. Single Phase Overhead Equipments, LT supply transformer and switching station in connection with Doubling work from Dakshin Barasat to Laksmikantapur in SEALDAH Division of Eastern Railway
Chief Electrical Engineer/CON, Eastern Railway,Kolkata.
Eastern Railway
23 TKM
29
Design, Supply, Erection, Testing, & Commissioning of 25 KV OHE for the work of: 1. Electrification of Development of coaching terminal facilities at Anand Vihar Ph.11 & Electric Loco Shed at Anand Vihar.2. Electrification of 3 Nos. Additional X-overs bet. UP GAL and 3rd & 4th line on Anand Vihar-SBB Section.3. Extension of existing Heavy Repair Shed in EMU Car Shed at Ghaziabad.4. Faridabad: Development of Freight Terminal at Faridabad.5. Construction of ROB at newly constructed Bye Pass Road near Sector 61 & 59 at kms. 1497/19-21 on Delhi-Palwal Section at Faridabad.6. Provision for Up-gradation of Washing Line No. 7 & 8 at New Delhi.
Chief Electrical Engineer/Const,Northern Railway,New Delhi.
Northern Railway
14 TKM
30
Design, Supply, Erection, Testing & Commissioning of 25 KV, AC, Single phase, 50 Hz, Traction Overhead Equipments, Switching Stations, Booster Transformer Stations and LT Supply transformer Stations in Krishnanagar (Excl)- Lalgola (Incl) section of Eastern Railway under RE project, Kolkata (128 RKMs/144 TKMs).
Chief Electrical Engineer, Railway Electrification, Allahabad.
Northern Railway
147.768 TKM
31
Supply, erection, testing & commissioning ,qf .25 KV OHE Tamluk – Kanthi section
Chief Electrical Engineer/CON, South Eastern Railway.
South Eastern Railway
60.793 TKM
32
Supply, Erection & Commissioning of 25 KV OHE over Kanthi-Digha Section
Chief Electrical Engineer/CON, South Eastern Railway.
South Eastern Railway
39.995 TKM
33
Design, Drawing, Supply, Erection, Testing & Commissiong of 25 KV AC, Single Phase, Overhead Equipment, Switching Station and LT Supply Transformer for electrification of double line between Kalinarayanpur-Badkulla & Baruipur-Dakshin Barasat in Sealdah Division of Eastern Railway.
Chief Electrical Engineer/CON, Eastern Railway, Fairly Place, Kolkata
Eastern Railway
37.861 TKM
34
Design, Supply, Erection,Testing & Commissioning of 25 KV OHE for the work Electrification of :-New line from CDG to Kharar
Chief Electrical Engineer(Con), N.Rly. New Delhi.
Northern Railway
25.192 TKM
35
Design, Supply, Erection, Testing & Commissioning of 25 KV OHE for the work of :- Electrification of 3rd line between Sahnewal-Ludhiana in connection with CDG-LDH new B.G. rail link.
Chief Electrical Engineer(Con), N.Rly. New Delhi.
Northern Railway
21.765 TKM
36
Design,Drawing,Supply,Erection,Testing and Commissioning of 25 KV a.c.Single Phase Overhead Equipments & LT Supply Transformer for Doubling Between Chandpara to Bongaon and Karea-Kadambagachi to Sondalia in Sealdah Division of Eastern Railway.
Chief Electrical Engineer(Con), E.Rly, Fairly Place,Kolkata.
Eastern Railway
21.208 TKM
37
Design, Drawing ,Supply, Erection ,Testing & Commissioning of 25 KV AC Single Phase Overhead equipment & switching station and LT supply transformer for Electrification of Double Line between Baruipur-Magrahat in Sealdah Division of Eastern Railway.”
Chief Electrical Engineer(Con), E.Rly, Fairly Place, Kolkata.
Eastern Railway
19 TKM
38
Design, Drawing, Supply, Erection, Testing & Commissioning of 25 KV AC Single phase OHE, Switching Station, LT Supply Transformer 7 Switching Station in connection with the work of Doubling from Ghutiari Shariff to Canning in Sealdah Division of Eastern Railway
Chief Electrical Engineer/CON, Eastern Railway, Fairly Place, Kolkata.
Eastern Railway
16.122 TKM
39
Design, Drawing, Supply, Erection, Testing & Commissioning of 25 KV AC Single phase Overhead Equipment, Switching station and LT Supply Transformer for complete Electrification of Chitpur yard in Sealdah Division of Eastern Railway
Chief Electrical Engineer/Con Eastern Railway, Fairly Place, Kolkata.
Eastern Railway
14 TKM
40
Design, Drawing, Supply, Erection, Testing & Commissioning of 25 KV a.c. Single Phase Overhead Equipment, LT supply transformer & modification of switching station etc. in connection with Doubling work from Bhagwangola to Jiaganj in SEALDAH Division of Eastern Railway
Chief Electrical Engineer/Con Eastern Railway, Fairly Place, Kolkata.
Eastern Railway
13.14 TKM
41
Electrification of New BG line from Kharar to New Morinda including Mohali/SSP.Kharar/SP,New Morinda/FP and Kurali/TSS”
Chief Electrical Engineer,Northern Railway Electrification,New Delhi.
Northern Railway
12.501 TKM
42
Design, Supply, Erection, Testing & Commissioning of 25KV OHE for the work of “Development of Freight Terminal Facilities at Chandigarh
Chief Electrical Engineer/Const,Northern Railway, New Delhi.
Northern Railway
2.132 TKM
43
Design, Supply, Erection, Testing & Commissiong of 25 KV OHE work of upgradation of 2 Nos Traction Power Transformers of 21.6 MVA,66KV/27KV at Ballavgarh TSS.
Chief Electrical Engineer(Con), N.Rly.New Delhi.
Northern Railway
TSS
44
Design, Supply, Erection, Testing & Commissioning for the work of “Provision of 2nd 220/KV/27KV Power Transformer of 21.6 MVA capacity at Traction Sub Substation, Ghaggar
Chief Electrical Engineer/Const,Northern Railway, New Delhi.
Northern Railway
TSS
45
Design, drawing, supply, erection, testing and commissioning of 25 KV AC OHE and switching station in connection with construction of Railway infrastructure of DSTPS of DVC at Andal, Durgapur
Group General Manager(P), RITES, Kolkata.
RITES
46
Design,Supply,Erection,Testing & Commissioning of 25 KV AC, 50 Hz Single phase, Traction Over head Equipments, Transformer Stations in Bharatpur Coliery siding at Talchar
Chief Project Manager, Railway Electrification,Bhubaneshwar.
Railway Electrification
47
Electrification of double line between Kargi Road Yard – Salka road in Bilaspur Division
Chief Electrical Engineer/Con, South Eastern Railway, Garden Reach, Kolkata.
RSouth Eastern Railway
48
25 KV A.C., Single phase, 50 Hz, Traction Overhead Electrification Work in Khana(Excl.)- Sainthia-Pakur(Incl.), Gr.162-A of Eastern Railway, under Railway Electrification Project Kolkata; Total 152 RKM/376 TKM.
Eastern Railway
376 TKM
49
132/25kV Traction Substation work at Rampurhat and Dubrajpur in Khana – Sainthia – Pakur and Pandabeswar – Sainthia SECTION (Group -162A&B).
Chief Administrative Office/Railway Electrification -Allahabad.
Eastern Railway
2 Nos TSS Work
50
Design, Supply, Erection, Testing & Commissioning of 25 KV, 50 Hz, Single Phase, Electrification Works including OHE, TSS, SCADA & Electric General Works on Turnkey Basis in Vizianagaram (Excl.) – Singapur Road (Incl.) Gr.166 of Waltair Division of East Coast Railway under RE Project Bhubaneswar (Total 138.84 RKM / 369 TKMs) – BCPL-EMC JOINT VENTURE.
Chief Administrative Office /Railway Electrification-Allahabad.
East Coast Railway
369 TKM including 3 nos Tss work
51
Design, Supply, Erection, Testing & Commissioning of 25 KV, 50 Hz, Single Phase Over Head Equipment including, TSS & SCADA Works in Kumedpur (Excl.) – Old Malda (Incl.) & Old Malda – Singhabad Section, Gr.171 of Katihar Division of North Frontier Railway under RE Project New Jalpaiguri, Total 79 RKM / 168 TKMs” – EMC-BCPL Joint Venture.
Chief Administrative Office/Railway Electrification – Allahabad.
North Frontier Railway
168 TKM
Sl No. Code Description of Work Total TKM/TSS Name of Employer/Client
1
REAF
Design, Supply, Erection, Testing and Commissioning of 25KV, 50 Hz, Single Phase AC, Electrification works including OHE & TSS Works as Composite Electrical Works in Azimganj (Incl.) – Nalhati (Excl.) & Azimganj-New Farakka/Tildanga (Excl.) section, Group-188-A & 189 including Sagardighi Thermal Power Station & Sonar Bangla Cement Siding in Azimganj – New Farakka section of Howrah &Malda Divisions of Eastern Railway under RE Project Danapur
79 RKM/ 152 TKM
Chief Administrative Office /Railway Electrification-Allahabad
2
MOD-DK
Design, Supply, Erection, Testing and Commissioning of 25KVAC Single Phase Overhead Equipment and LT Supply Transformer for Modification of Dankuni Yard and Modification of OHE at Kamarkundu including Feeder line work as Part-III of Dankuni-Chandanpur 4th Line in Howrah Division of Eastern Railway
OHE/TSS
Dy.Chief Electrical Engineer/Construction/ Howrah
3
Batala
Design, Supply, Erection, Testing and Commissioning of 25KV Single phase OHE work of Electrification of Batala- Qadian Section over Firozpur Division
OHE/TSS
Dy.Chief Electrical Engineer/Construction/ Northern Railway/ Jalandhar
4
KJP
Design, Supply, Erection, Testing and Commissioning of switching stations SSP at Khana & modification of SP at Jhapterdhal in Eastern Railway in connection with Railway Electrification work of Gr.162A in Howrah Division of Eastern Railway
SP/SSP/ OHE
Dy.Chief Electrical Engineer/Railway Electrification/ Kolkata
5
LJ
Design, Supply, Erection, Testing and Commissioning of 25KV, 50 Hz, Single Phase AC, Electrification works including OHE & TSS Works as Composite Electrical Works in Lanjigarh Road -Junagarh Section,Gr.346 in Sambhalpur Division of East Coast Railway,under RE Project Bhubaneswar
OHE/TSS
Chief Administrative Office /Railway Electrification-Allahabad
6
REAK
Design, Supply, Erection, Testing and Commissioning of 25KV, 50 Hz, Single Phase AC, Electrification works including OHE & TSS Works as Composite Electrical Works in Katwa (EXCL)-Azimgunj(EXCL) Section in Howrah Division Gr. 188B under RE Project Kolkata
72.74 RKM/160TKM
Chief Administrative Office /Railway Electrification-Allahabad.
7
RE NBK
Design, Supply, Erection, Testing and Commissioning of 25KV, 50 Hz, Single Phase AC, Electrification works including OHE & TSS Works as Composite Electrical Works in new Bongaigaon (EXCL)-Goalpara Town- Kamakhya(EXCL) Section in Rangiya Division Gr. 256 under RE Project New jalpaiguri, Northeast Frontier Railway
175.5 RKM/210 TKM
Chief Administrative Office /Railway Electrification-Allahabad.
8
SGR
Design, Supply, Erection, Testing and Commissioning of 25KV, 50 Hz, Single Phase AC, Electrification works including OHE works in Raninagar Jalpaiguri (EXCL)-Jalpaiguri Road(INCL)& Gumanihat(INCL)-Samuktala Road(INCL) 2nd line Section, Gr.255 in Alirpurduar Division New Jalpaiguri, Northeast Frontier Railway.
66.72 RKM/77 TKM
Chief Administrative Office /Railway Electrification-Allahabad.
9
BEAS
Design, Supply, Erection, Testing and Commissioning of 25KV, 50 Hz, Single Phase AC, including OHE & TSS for the work of Electrification of BEAS-Goindwal-Tarn Taran Amritsar Section of Firojpur Division
OHE/TSS
Chief Electrical Engineer(c),Tilak Bridge,New Delhi
10
KAM
Design, Supply, Erection, Testing and Commissioning of 25KV, 50 Hz, Single Phase Overhead Equipment,LTSupply Transformer,Modification of Switching Station at Ahmadpur,New Switching Station At Labpur,Kirnahar,Jnandaskendra,Panchandi Along with Modification of SCADA equipments in connection with Electrification BG line from Ahmedpur to Katwa in Howrah Division of Eastern Railway
LT/SSP/SCADA
Dy. Chief Electrical Engineer/con,Howrah
11
RESD
Design, Supply, Erection, Testing and Commissioning of 25KV, 50 Hz, Single Phase AC, Electrification works including OHE & TSS Works as composite Electrical Works in Singapur Road (Excl) – Damanjodi (Incl) Section, Gr 181 of Waltair Division of East Coast Railway under RE Project Bhubaneswar, Total 152 RKM/179 TKMs
179 TKM
Chief Administrative Office /Railway Electrification-Allahabad.
12
Rungta
DDesign, Supply, Erection, Testing,Approval & Commissioning of 25KV, 50 Hz, Single Phase Conventional type Regulated OHE & SSP to serve M/s Rungta Mines Limited at Chakradharpur Railway Division, South Eastern Railway
SSP/OHE
Rungta Mines Limited
13
KNC
Design, Supply, Erection, Testing,Approval & Commissioning of 25KV, 50 Hz, Single Phase Conventional type Regulated OHE to serve M/s Khatau Narbheram & Co. at Bolani Khadan,Barbil at Chakradharpur Railway Division, South Eastern Railway
OHE
Khatau Narbheram & Co
14
RRTS
Tikiapara-Shyamchak-Howrah-Kharagpur ; Rehabilitation Renewal of OHE of Suburban Section(Phase-1)
OHE
Sr. Divisional Electrical Engineer ,Kharagpur Division(TR)D
15
REPQR
Design, Supply, Erection, Testing and Commissioning of 25KV, 50 Hz, Single Phase AC, Electrification works of OHE & SWS Work in Pakur query Siding;Rajgram Stone Siding & Panem Coal Siding at Pakur in Rampurhat- Pakur Section of Howrah Railway Division,Eastern Railway.
6.3 RKM/17.5 TKM
Chief Project Director,Kolkata, Eastern Railway
16
Tata Steel BSL Ltd
OHE Work for In-plant yard Pre-Tippler line no 7,8,9 and post tippler line no 1,1B, 1C, 4,5 including By pass line at Meramandali, Odhisha.
9.932
Tata Steel BSL Limited
17
TNAR
25KV Switching Station at Naihati, Kanchrapara, Chakdaha and Ranaghat Feeding Post including Modification of Kalyani Switching Station in connection with construction of 3rd line from Naihati to Ranaghat in Sealdah Division of Eastern Railway.
SP/SSP/FP
Chief Electrical Engineer/CON, Eastern Railway, Kolkata.
18
Katwa TSS -II
Design, Drawing, Supply, Erection, Testing & Commissioning of 2nd Bay for 132KV/25KV Traction Sub-Station at Katwa in Howrah Division of Eastern Railway
TSS
Deputy Chief Electrical Engineer/CON, Eastern Railway, Howrah.
19
UC-DNK
Supply, Erection and Civil work of OHE for Railway Siding and Dankuni Cement Works, unit of UltraTech Cement Ltd., Vill. Panchghara, P.O. Panchghara Bazar, P.S.Chanditala, Dist. Hooghly, West Bengal
OHE
UltraTech Cement Limited
© Copyright 2024. All Rights Reserved by